RERA’d by NeevHQ

Projects · BD INFRADEVELOPERS LLP

Ultimus

Bd Infradevelopers · Sector 90, Gurugram

Registered with RERA: Jan 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Bd Infradevelopers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameULTIMUS
Builder (promoter)BD INFRADEVELOPERS LLP
LocationSECTOR 90 GURUGRAM
RERA project IDRERA-GRG-989-2021
Registration certificate numberGGM/530/262/2022/05 DATED 31.01.2022
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to14/07/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area2.3375 acres
Licence39 of 2021
Estimated cost of the project₹10,995.59 lakh (₹109.96 crore)
Total units (plots, apartments, shops)344
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder2 BHK: 622–644 sq ft carpet (source: the builder's floor plans uploaded to HRERA)
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on05-01-2022
Building plans approved on05-01-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-03-2022
Likely completion date14-07-2026

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on25-Sep-2026
Quarterly reports listed on the portal17

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹3 lakh (₹0.03 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹71.17 lakh (₹0.71 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹84.03 lakh (₹0.84 crore)
Project bank account (escrow): deposited in the quarter₹2.1 lakh (₹0.02 crore)
Project bank account (escrow): withdrawn in the quarter₹2.1 lakh (₹0.02 crore)
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)383 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹279.04 lakh (₹2.79 crore) paid; ₹0 due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Jun 2026
Overall work complete99%
By part
  • Tower C1: G+14 completed
  • Tower C2: G+14 completed
  • Tower D1: G+13 completed
  • Sub structure (all towers): 100%
  • Super structure (all towers): 100%
  • Mechanical MEP (lifts, ventilation): 100%
  • Electrical MEP (conduiting, wiring, fixtures): 95%
  • Plumbing and firefighting (piping, pumps, fixtures): 95%
  • Internal finishing (plaster, tiling, flooring, painting): 99%
  • External finishing (plaster, painting, facade): 98%
  • Walls on floors (Towers C1, C2, D1): 80%, 44 floors walled
  • Lift wells with waterproofing (Towers C1, C2, D1): 80%, 6 lift wells
  • Lift lobbies and common areas floor wise (Towers C1, C2, D1): 60%, 44 floors
  • Fixing of door and window frames in flats (Towers C1, C2, D1): 40%
  • Sanitary fixtures within flats (Towers C1, C2, D1): 35%
  • Electrical fittings within flats (Towers C1, C2, D1): 35%
  • Internal roads and pavements: 95%
  • Shopping area (commercial): 99%
  • Street lighting and electrification: 95%
Unclear in the certificate
  • No quarter is named in the certificate, so the quarter end date is not stated.
  • The overall 99.0% figure in Annexure A is dated 31 Mar 2026, while the certificate is dated 30 Jun 2026.
  • Tower-wise percentages are not given; Table A figures cover Towers C1, C2 and D1 together.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusPending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against BD INFRADEVELOPERS LLP (all its projects)2 (Complaint: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in