Projects · PYRAMID INFRATECH PVT. LTD.

Urban 67-A

Pyramid Infratech · Sector 67, Gurugram

Registered with RERA: Nov 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Pyramid Infratech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameURBAN 67-A
Builder (promoter)PYRAMID INFRATECH PVT. LTD.
LocationSECTOR-67-A, GURUGRAM, HARYAN A
RERA project IDRERA-GRG-680-2020
Registration certificate number350 OF 2017 DATED 17.11.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/10/2022
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area9.83125 acres
Licence10 of 2016
Estimated cost of the project₹29,603.6 lakh (₹296.04 crore)
Total units (plots, apartments, shops)1494
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder2 BHK: 578–598 sq ft carpet, 1,330 units (source: the builder's registration form (Form A-H))
Units booked when registered1379
Units unsold when registered115
Layout plan approved on02-11-2017
Building plans approved on02-11-2017

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date12-02-2022
Revised completion date22-02-2022
Infrastructure: projected completion12-02-2022
Infrastructure: percentage complete when registered12.30%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusFirst Hearing: 3; Online Complaint Not Yet Received At Office: 1; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against PYRAMID INFRATECH PVT. LTD. (all its projects)58 (Complaint: 56; Compensation: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in