RERA’d by NeevHQ

Projects · PYRAMID INFRATECH PVT. LTD.

Urban Homes

Pyramid Infratech · Sector 70A, Gurugram

Registered with RERA: Oct 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Pyramid Infratech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameURBAN HOMES
Builder (promoter)PYRAMID INFRATECH PVT. LTD.
LocationSECTOR 70A, GURUGRAM
RERA project IDRERA-GRG-681-2020
Registration certificate number254 OF 2017 DATED 03.10.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to28/02/2020
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area9.875 acres
Licence116 OF 2014
Estimated cost of the project₹28,858.22 lakh (₹288.58 crore)
Total units (plots, apartments, shops)1721
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder1 BHK: 334–342 sq ft carpet, 207 units; 2 BHK: 501–516 sq ft carpet, 1,406 units (source: the builder's registration form (Form A-H))
Units booked when registered1617
Units unsold when registered104
Layout plan approved on03-08-2015
Building plans approved on03-08-2015

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date15-02-2020
Revised completion date15-02-2020
Infrastructure: projected completion15-02-2020
Infrastructure: percentage complete when registered100%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed7
By statusFirst Hearing: 4; Online Complaint Not Yet Received At Office: 1; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project3
Cases
Decided cases against PYRAMID INFRATECH PVT. LTD. (all its projects)58 (Complaint: 56; Compensation: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in