Projects · M/S VATIKA ONE INDIA NEXT PVT. LTD.

Vatika Crossover

M/S Vatika One India Next · Sector 82A, Gurugram

Registered with RERA: Jan 2023

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: M/S Vatika One India Next

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameVATIKA CROSSOVER
Builder (promoter)M/S VATIKA ONE INDIA NEXT PVT. LTD.
LocationSECTOR-82A, VILLAGE-SHIKOHPUR , GURUGRAM
RERA project IDRERA-GRG-1192-2022
Registration certificate numberGGM/680/412/2023/24 DATED 30.01.2023
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to29/06/2025
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area9.66 acres
Licence165 of 2022 Dated 13.10.2022 and valid up to 12.10.2027
Estimated cost of the project₹19,227.28 lakh (₹192.27 crore)
Total units (plots, apartments, shops)98
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on01-10-2022
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-10-2022
Likely completion date30-06-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on03-Nov-2026
Quarterly reports listed on the portal14

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹591.93 lakh (₹5.92 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹844.04 lakh (₹8.44 crore)
Other costs in the quarter (EDC, taxes, etc.)₹22,158.73 lakh (₹221.59 crore)
Project bank account (escrow): deposited in the quarter₹414.36 lakh (₹4.14 crore)
Project bank account (escrow): withdrawn in the quarter₹373 lakh (₹3.73 crore)
Project bank account (escrow): balance at quarter end₹172.35 lakh (₹1.72 crore)
Units in the project (apartments / plots)98 plots
Sold in the quarter5 plots
EDC (development charges): paid / due as on date₹4,608.69 lakh (₹46.09 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 13-10-2022
  • Demarcation Plan: Obtained Approval 12-12-2022
  • Zoning Plan: Obtained Approval 12-12-2022
  • Electricity Plans: Obtained Approval 16-12-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Sub structure (Table A, tower number not filled): 100%
  • Super structure (Table A): not stated
  • MEP - Mechanical (Table A): not stated
  • MEP - Electrical (Table A): 98.07%
  • MEP - Plumbing & Firefighting (Table A): 95.97%
  • Finishing - Internal (Table A): not stated
  • Finishing - External (Table A): 93.43%
  • Underground water tank (Table B): 74%
Unclear in the certificate
  • Table A has no building or tower number filled in, so it is not clear which tower it covers.
  • Table B does not name a tower; the 74% for the underground water tank is the only figure in that table.
  • Most Table B items are marked NA, so no percentage is given for them.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusDisposed: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against M/S VATIKA ONE INDIA NEXT PVT. LTD. (all its projects)6 (Complaint: 5; Execution of an earlier order: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in