Projects · M/S VATIKA ONE INDIA NEXT PVT. LTD.
Vatika Crossover
M/S Vatika One India Next · Sector 82A, Gurugram
Registered with RERA: Jan 2023
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jun 2025)
- HRERA opened a case of its own against the builder in Aug 2023 (closed):
- Why: did not submit approved service plans and estimates within three months (due 30 Apr 2023)
- Latest: case disposed of 22 Mar 2024; judgement uploaded same day
- At stake: ₹25 lakh service plan security forfeited; QPR security ordered refunded
Will it be delivered on time?
- Original deadline Jun 2024, extended to Jun 2025
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: Sub structure
- In progress: Electrical 98.07%, Plumbing & firefighting 95.97%, External finishing 93.43%, Underground water tank 74%
- Money: ₹230 crore spent of ₹266.1 crore; ₹36 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 98 units: 75 sold, 23 unsold (builder's certificate, Sep 2026)
- Appartment: 75 of 98 sold
- Registration now covers 98
- 98 plots, 95–360 sq yd
Location
- Nearest metro: Millennium City Centre Gurugram, 17.6 km by road (47 min by car)
- Cyber City 53 min · Airport 44 min by car at 9:30 am
- Within 3 km: 2 hospitals, 1 school, 0 malls
The builder: M/S Vatika One India Next
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 6 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | VATIKA CROSSOVER |
|---|---|
| Builder (promoter) | M/S VATIKA ONE INDIA NEXT PVT. LTD. |
| Location | SECTOR-82A, VILLAGE-SHIKOHPUR , GURUGRAM |
| RERA project ID | RERA-GRG-1192-2022 |
| Registration certificate number | GGM/680/412/2023/24 DATED 30.01.2023 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 29/06/2025 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 9.66 acres |
| Licence | 165 of 2022 Dated 13.10.2022 and valid up to 12.10.2027 |
| Estimated cost of the project | ₹19,227.28 lakh (₹192.27 crore) |
| Total units (plots, apartments, shops) | 98 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 01-10-2022 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-10-2022 |
|---|---|
| Likely completion date | 30-06-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 03-Nov-2026 |
| Quarterly reports listed on the portal | 14 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹591.93 lakh (₹5.92 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹844.04 lakh (₹8.44 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹22,158.73 lakh (₹221.59 crore) |
| Project bank account (escrow): deposited in the quarter | ₹414.36 lakh (₹4.14 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹373 lakh (₹3.73 crore) |
| Project bank account (escrow): balance at quarter end | ₹172.35 lakh (₹1.72 crore) |
| Units in the project (apartments / plots) | 98 plots |
| Sold in the quarter | 5 plots |
| EDC (development charges): paid / due as on date | ₹4,608.69 lakh (₹46.09 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Disposed: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against M/S VATIKA ONE INDIA NEXT PVT. LTD. (all its projects) | 6 (Complaint: 5; Execution of an earlier order: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in