Projects · VIPUL LIMITED
Vipul Lavanya Apartments-Tower 2&3
Vipul · Sector 81, Gurugram
Registered with RERA: Sep 2018
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Aug 2019)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit a quarterly progress report (May 2022, open)
- Did not apply to extend registration or submit completion, part completion or occupation certificate; requisite documents (Jun 2022, open)
- Did not complete Vipul Lavanya Apartments Towers 2&3 within the declared time (Jun 2022, open)
- 3 more cases: reply 4
- 17 complaints about this project decided by HRERA since Nov 2023 (16 delay interest ordered, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Sep 2020, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
Location
- Nearest metro: Millennium City Centre Gurugram, 22 km by road (54 min by car)
- Cyber City 60 min · Airport 48 min by car at 9:30 am
- Within 3 km: 1 hospital, 1 school, 0 malls
The builder: Vipul
- 3 projects registered in Gurugram, 3 lapsed
- 0 with an occupation certificate on record
- 97 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | VIPUL LAVANYA APARTMENTS-TOWER 2&3 |
|---|
| Builder (promoter) | VIPUL LIMITED |
|---|
| Location | SECTOR-81,GURUGRAM |
|---|
| RERA project ID | RERA-GRG-309-2019 |
|---|
| Registration certificate number | GGM/283/2018/15 DATED 11.09.2018 |
|---|
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 31/08/2019 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 2.282 acres |
|---|
| Licence | 26 of 2010 |
|---|
| Estimated cost of the project | ₹6,394 lakh (₹63.94 crore) |
|---|
| Total units (plots, apartments, shops) | 116 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 103 |
|---|
| Units unsold when registered | 13 |
|---|
| Layout plan approved on | 07-09-2010 |
|---|
| Building plans approved on | 07-09-2010 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 01-01-2016 |
|---|
| Revised completion date | 30-09-2020 |
|---|
| Infrastructure: projected completion | 01-08-2019 |
|---|
| Infrastructure: percentage complete when registered | 100% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 15-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 32 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 116 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹1,325 lakh (₹13.25 crore) paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 24-01-2011
- Zoning Plan: Obtained Approval 07-09-2010
- Service Plans: Obtained Approval 07-09-2010
- Electricity Plans: Obtained Approval 30-10-2010
- Site Plans: Obtained Approval 12-07-2010
- Building Plans: Obtained Approval 12-07-2010
- Fire NOC: Obtained Approval 14-09-2012
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026 |
|---|
| By part | - Tower 2: Excavation, raft and pile foundations 100%. Walls, staircase, lift wells, lobbies and door and window frames 100%. MEP internal and external works 100%. Building has 3 basements and G+14 floors, with ground as stilt/ground floor.
- Tower 3: Excavation, raft and pile foundations 100%. Walls, staircase, lift wells, lobbies and door and window frames 100%. MEP internal and external works 100%. Building has 3 basements and G+14 floors, with stilt as stilt/ground floor.
|
|---|
| Unclear in the certificate | - Table A has no tower name filled in, so its cumulative percentages (sub-structure 100%, super-structure 100%, mechanical 100%, electrical 100%, plumbing and firefighting 96%, internal finishing 97%, external finishing 95%) cannot be tied to a specific tower.
- The quarter the certificate covers is not stated, and the work done during the quarter columns are blank.
- The date field at the bottom of the certificate is blank; the date used is the date of certifying the percentage of work.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | First Hearing: 3; Pending: 3 |
|---|
| Proceedings | - RERA-GRG-3378-2022: Case RERA-GRG-3378-2022, listed as HARERA Gurugram through an individual versus VIPUL LIMITED. The page shows a first hearing and a notice under 'Compliance us 42ld', but it does not state the reason for the case. Status: First hearing was listed for 30 Jun 2022. The listing status is 'FIRST HEARING', with no proceedings or order recorded. Latest: 30 Jun 2022, A document was submitted by the individual named on the page and recorded as a new complaint.
- RERA-GRG-3584-2022: The Authority issued a show cause notice to the promoter, Vipul Limited, for not submitting a quarterly progress report. The notice asked the promoter to appear before the Authority on 27 Jun 2022 with a written reply if it had anything to say. Status: Listed for first hearing on 27 Jun 2022. The page records no proceedings or order for that hearing yet. Latest: 27 Jun 2022, First hearing listed. Status shown as 'FIRST HEARING' with no proceedings, bench order or order uploaded on the page.
- RERA-GRG-3919-2022: The Authority issued a show cause notice to the promoter Vipul Limited for not applying for extension of registration, not submitting a completion, part completion or occupation certificate, and not submitting the requisite documents. Status: First hearing was listed for 28 Jun 2022. The case page shows the status as First Hearing, with no proceedings or order recorded for that day. Latest: 28 Jun 2022, First hearing listed. The case page shows the status as First Hearing, with no proceedings, bench order or order uploaded.
- RERA-GRG-3920-2022: The Authority started a suo motu case against Vipul Limited for not finishing its project (Vipul Lavanya Apartments Tower 2&3) within the time it had declared, which is a violation of section 4(2)(l)(C) of the Real Estate (Regulation and Development) Act, 2016. Status: Pending. The matter is listed for hearing on 23 Jul 2025. The promoter has often not been present at hearings. Latest: 10 Jun 2025, The matter was listed to come up on 23 Jul 2025.
- RERA-GRG-4298-2022: Suo-motu proceedings by the Authority against Vipul Limited for not meeting conditions of the registration certificate for Vipul Lavanya Apartments Tower 2&3, Gurugram. The promoter was asked to submit documents and show cause why its registration should not be revoked. Status: Pending. As of the last recorded proceedings (02 Dec 2022), the promoter had not submitted the required documents. A reply to the show cause notice was filed on 16 Dec 2022. The matter is adjourned to 20 Jan 2023. Latest: 16 Dec 2022, Reply to the show cause notice received from the promoter. Matter adjourned to 20 Jan 2023.
- RERA-GRG-5644-2019: The Authority's own proceeding against promoter Vipul Limited about compliance notices under Section 42, scrutiny of the REP-I Part (A-H) form and a quarterly progress report (QPR). Status: Pending. The last recorded listing shows the next hearing on 17 Feb 2020 with status PENDING, and no proceedings are recorded for that date. Latest: 16 Jul 2020, Third notice under Section 42 dispatched to the promoter. The complaint was also dispatched on this date (tracking ID EH770720034IN).
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 17 |
|---|
| Cases | - RERA-GRG-3510-2025 (complaint, decided 17-Jul-2026): Buyer's delay possession and conveyance deed claims; builder ordered to pay 10.80% delay interest and execute conveyance deed.
- RERA-GRG-3515-2025 (complaint, decided 22-May-2026): Buyer bought resale in 2024; delay charges refused; builder ordered to register conveyance deed within three months of occupancy certificate.
- RERA-GRG-3518-2025 (complaint, decided 22-May-2026): Buyer sought delay compensation and conveyance deed; builder ordered to pay 10.80% delay interest and execute conveyance deed.
- RERA-GRG-3291-2025 (complaint, decided 22-May-2026): Buyers sought delay interest and conveyance deed; builder ordered to pay 10.80% interest and execute deed.
- RERA-GRG-4260-2025 (complaint, decided 13-Feb-2026): Buyers sought delay charges and conveyance deed; no delay charges; builder must register deed within 3 months of occupation certificate.
- RERA-GRG-4024-2025 (complaint, decided 13-Feb-2026): Buyers sought delay charges and conveyance deed; delay charges refused, builder must register deed within 3 months of occupancy certificate.
- RERA-GRG-3099-2023 (compensation, decided 13-Feb-2026): Buyer sought extra compensation over delayed flat possession; complaint dismissed as delay interest was already allowed.
- RERA-GRG-3547-2025 (complaint, decided 13-Feb-2026): Buyers sought delayed possession charges and conveyance deed; builder ordered to register conveyance deed after occupancy certificate.
- RERA-GRG-3566-2025 (complaint, decided 13-Feb-2026): Buyers sought possession, delay charges and conveyance deed; delay charges declined, builder ordered to execute conveyance deed after occupancy certificate.
- RERA-GRG-3522-2023 (complaint, decided 08-May-2025): Buyer sought delay interest and conveyance deed for flat; builder ordered to pay 11.10% interest for 21 days delay and execute conveyance deed after occupancy certificate.
- RERA-GRG-1874-2024 (complaint, decided 04-Apr-2025): Buyers sought possession after delay; builder ordered to hand over flat and pay 11.10% delay interest from Jan 2015.
- RERA-GRG-213-2024 (complaint, decided 05-Mar-2025): Buyer sought possession with delay interest after 2015 due date; HRERA ordered builder to pay 11.10% interest until possession in Oct 2023.
- RERA-GRG-5447-2023 (complaint, decided 28-Aug-2024): Buyer sought possession with interest after delay; builder ordered to pay 11.10% delay interest and hand over possession after occupation certificate.
- RERA-GRG-616-2021 (complaint, decided 09-Apr-2024): Buyer sought possession and delay interest after possession was due 31 Aug 2019; HRERA ordered 10.85% delay interest and possession and conveyance deed after occupancy certificate.
- RERA-GRG-583-2021 (complaint, decided 09-Apr-2024): Buyer sought possession and delay interest after possession was due 31 Aug 2019; HRERA ordered 10.85% delay interest and possession and conveyance deed after occupancy certificate.
- RERA-GRG-6449-2022 (complaint, decided 24-Nov-2023): Buyer sought possession and delay interest; builder ordered to pay 10.75% delay interest and offer valid possession after occupation certificate.
- RERA-GRG-6356-2022 (complaint, decided 24-Nov-2023): Buyer sought possession and delay interest for a flat in Vipul Lavanya; builder ordered to offer possession after occupation certificate and pay 10.75% delay interest.
|
|---|
| Decided cases against VIPUL LIMITED (all its projects) | 97 (Complaint: 81; Execution of an earlier order: 14; Compensation: 2) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in