Waterfall Residence

Krisumi Corporation · Sector 36A, Gurugram

Registered with RERA: May 2018

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Krisumi Corporation

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameWATERFALL RESIDENCE
Builder (promoter)KRISUMI CORPORATION PRIVATE LIMITED
LocationVILLAGE SIHI & HARSARU,SECTOR -36A,GURUGRAM-MANESAR
RERA project IDRERA-GRG-197-2019
Registration certificate numberGGM/271/2018/03 DATED 08.05.2018
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area27.48125 acres
Licence. 39 dated 04.06.2013 and renewed on 14.07.2017 and Licence No 85 of 2014.
Estimated cost of the project₹35,711 lakh (₹357.11 crore)
Total units (plots, apartments, shops)433
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered0
Units unsold when registered433
Layout plan approved on12-01-2018
Building plans approved on12-01-2018

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2023
Revised completion date30-06-2024
Infrastructure: projected completion30-06-2024
Infrastructure: percentage complete when registered0.3%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2024 (OCT-DEC)
Latest report submitted on14-Jan-2025
Quarterly reports listed on the portal25

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2024 (OCT-DEC))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹4,040.28 lakh (₹40.4 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹741.01 lakh (₹7.41 crore)
Spent on infrastructure in the quarter₹4,479.31 lakh (₹44.79 crore)
Other costs in the quarter (EDC, taxes, etc.)₹1,302.54 lakh (₹13.03 crore)
Project bank account (escrow): deposited in the quarter₹2,507.13 lakh (₹25.07 crore)
Project bank account (escrow): withdrawn in the quarter₹1,668.13 lakh (₹16.68 crore)
Project bank account (escrow): balance at quarter end₹841.1 lakh (₹8.41 crore)
Units in the project (apartments / plots)433 apartments
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹3,585.51 lakh (₹35.86 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 07-09-2017
  • Demarcation Plan: Obtained Approval 03-05-2013
  • Zoning Plan: Obtained Approval 04-06-2013
  • Service Plans: Obtained Approval 25-04-2022
  • Electricity Plans: Obtained Approval 05-01-2022
  • Site Plans: Obtained Approval 10-10-2017
  • Building Plans: Obtained Approval 12-01-2018
  • Fire NOC: Obtained Approval 25-04-2019

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 07 Jan 2025, for 31 Dec 2024
By part
  • Tower A: 100%, All 24 slabs laid by end of quarter; all listed sub-structure, super-structure, MEP and finishing items certified at 100%
  • Tower B: 100%, All 27 slabs laid by end of quarter; all listed sub-structure, super-structure, MEP and finishing items certified at 100%
  • Tower C: 100%, All 34 slabs laid by end of quarter; all listed sub-structure, super-structure, MEP and finishing items certified at 100%

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed3
By statusScrutinized: 1; First Hearing: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against KRISUMI CORPORATION PRIVATE LIMITED (all its projects)10 (Complaint: 2; Compensation: 8)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026