Projects · KRISUMI CORPORATION PRIVATE LIMITED
Waterfall Suites
Krisumi Corporation · Sector 36A, Gurugram
Registered with RERA: May 2023
Is it legal?
- RERA registered, valid till Dec 2028
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Dec 2028, never extended
- No occupation certificate yet (not ready for possession)
- Money: ₹154.5 crore spent of ₹281.3 crore; ₹126.8 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 320 units: 318 sold, 2 unsold (builder's certificate, Sep 2026)
- Sizes declared at registration (380 units):
- 1 unit of 1,689 sq ft carpet (1 tower)
- 58 units of 2,073 sq ft carpet (1 tower)
- 1 unit of 2,311 sq ft carpet (1 tower)
- 128 units of 4,996 sq ft carpet (1 tower)
- 62 units of 5,312 sq ft carpet (1 tower)
- 128 units of 6,368 sq ft carpet (1 tower)
- 2 units: the size the builder entered is not possible, so it is not shown
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 15.6 km by road (46 min by car)
- Cyber City 51 min · Airport 42 min by car at 9:30 am
- Within 3 km: 3 hospitals, 1 school, 0 malls
Location shown for Sector 36A; the exact site was not found.
The builder: Krisumi Corporation
- 7 projects registered in Gurugram
- 1 with an occupation certificate on record
- 10 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | WATERFALL SUITES |
|---|---|
| Builder (promoter) | KRISUMI CORPORATION PRIVATE LIMITED |
| Location | SECTOR 36A |
| RERA project ID | RERA-GRG-1302-2023 |
| Registration certificate number | GGM/715/447/2023/59 DATED 08.05.2023 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2028 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 3.886 acres |
| Licence | 39 of 2013 (valid till 03.06.2026) 85 of 2014 (valid till 07.08.2024) |
| Estimated cost of the project | ₹28,129.25 lakh (₹281.29 crore) |
| Total units (plots, apartments, shops) | 380 |
| Unit sizes (carpet area, as declared) | 1 unit of 1,689 sq ft carpet (1 tower); 58 units of 2,073 sq ft carpet (1 tower); 1 unit of 2,311 sq ft carpet (1 tower); 128 units of 4,996 sq ft carpet (1 tower); 62 units of 5,312 sq ft carpet (1 tower); 128 units of 6,368 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 14-12-2022 |
| Building plans approved on | 25-01-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-05-2023 |
|---|---|
| Likely completion date | 31-12-2028 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 13-Oct-2026 |
| Quarterly reports listed on the portal | 13 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹3,692 lakh (₹36.92 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹1,576.5 lakh (₹15.77 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹9.05 lakh (₹0.09 crore) |
| Project bank account (escrow): deposited in the quarter | ₹2,696.17 lakh (₹26.96 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹1,891.14 lakh (₹18.91 crore) |
| Project bank account (escrow): balance at quarter end | ₹9,860.42 lakh (₹98.6 crore) |
| Units in the project (apartments / plots) | 320 apartments |
| Sold in the quarter | 2 apartments |
| EDC (development charges): paid / due as on date | ₹1,552.92 lakh (₹15.53 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 05 Oct 2026, for 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against KRISUMI CORPORATION PRIVATE LIMITED (all its projects) | 10 (Complaint: 2; Compensation: 8) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in