Projects · KRISUMI CORPORATION PVT. LTD.
Waterside Residences The Forest Reserve
Krisumi Corporation · Sector 36A, Gurugram
Registered with RERA: May 2025
Is it legal?
- RERA registered, valid till Jun 2031
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Jun 2031, never extended
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- In progress: Wr 7.1 33.01%, Wr 7.2 33.01%
- Money: ₹126.5 crore spent of ₹1,427.7 crore; ₹1,301.2 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 298 units: 19 sold, 279 unsold (builder's certificate)
- 298 units in 7 sizes, as declared to HRERA:
- 3 units of 1,191 sq ft carpet (1 tower)
- 141 units of 1,503 sq ft carpet
- 3 units of 1,704 sq ft carpet (1 tower)
- 143 units of 1,996 sq ft carpet
- 4 units of 3,050 sq ft carpet (1 tower)
- 2 units of 3,441 sq ft carpet (1 tower)
- 1 less common size: see the full list below
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 15.9 km by road (46 min by car)
- Cyber City 51 min · Airport 42 min by car at 9:30 am
- Within 3 km: 2 hospitals, 1 school, 0 malls
The builder: Krisumi Corporation
- 7 projects registered in Gurugram
- 1 with an occupation certificate on record
- 10 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | WATERSIDE RESIDENCES THE FOREST RESERVE |
|---|---|
| Builder (promoter) | KRISUMI CORPORATION PVT. LTD. |
| Location | SECTOR- 36A |
| RERA project ID | RERA-GRG-1886-2025 |
| Registration certificate number | GGM/944/676/2025/47 DATED 02.05.2025 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/06/2031 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.1743 acres |
| Licence | 39 of 2013 dated 4.6.2013, 85 of2014 dated 8.8.2014 , 166 of 2023 dated 18.10.2023 and 71 of 2024 dated 28.06.2024 |
| Estimated cost of the project | ₹1,42,982.74 lakh (₹1,429.83 crore) |
| Total units (plots, apartments, shops) | 298 |
| Unit sizes (carpet area, as declared) | 3 units of 1,191 sq ft carpet (1 tower); 141 units of 1,503 sq ft carpet; 3 units of 1,704 sq ft carpet (1 tower); 143 units of 1,996 sq ft carpet; 4 units of 3,050 sq ft carpet (1 tower); 2 units of 3,441 sq ft carpet (1 tower); 2 units of 3,787 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 23-01-2025 |
| Building plans approved on | 23-01-2025 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-06-2025 |
|---|---|
| Likely completion date | 30-06-2031 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 14-Oct-2026 |
| Quarterly reports listed on the portal | 5 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹1,534.76 lakh (₹15.35 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹1,307.75 lakh (₹13.08 crore) |
| Spent on construction of apartments in the quarter | ₹2,858.33 lakh (₹28.58 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹219.02 lakh (₹2.19 crore) |
| Project bank account (escrow): deposited in the quarter | ₹1,119.48 lakh (₹11.19 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹1,166.38 lakh (₹11.66 crore) |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 298 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹2,712.98 lakh (₹27.13 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 01 Oct 2026, for 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against KRISUMI CORPORATION PVT. LTD. (all its projects) | 10 (Complaint: 2; Compensation: 8) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in