Projects · EXPERION DEVELOPERS PRIVATE LIMITED
Westerlies
Experion Developers · Sector 108, Gurugram
Registered with RERA: Nov 2019
Is it legal?
- RERA registered, valid till Jan 2024 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit the quarterly progress report (May 2022, open)
- Did not apply to extend registration or submit completion or occupation certificate (Jun 2022, open)
- Did not complete project within the time it declared (Jun 2022, open)
- 3 more cases: reply 4
- 10 complaints about this project decided by HRERA since Nov 2023 (4 delay interest ordered, 1 refund ordered, 2 other orders, 3 dismissed, withdrawn or settled)
Will it be delivered on time?
- Original deadline not found, extended to Jan 2024
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jan–Mar 2024):
- Done: 12 parts
- In progress: Community centre 0%, Schools 0%, Dispensary 0%, Creche 0%, Nursery school 0%, Taxi stand 0%, and 4 more
- Money: ₹41.8 crore spent of ₹41.9 crore (CA certificate, Mar 2024)
What's on offer?
- Registration now covers 123
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 10.6 km by road (22 min by car)
- Cyber City 60 min · Airport 41 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
The builder: Experion Developers
- 16 projects registered in Gurugram, 3 lapsed
- 6 with an occupation certificate on record
- 74 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | WESTERLIES |
|---|
| Builder (promoter) | EXPERION DEVELOPERS PRIVATE LIMITED |
|---|
| Location | SECTOR 108 |
|---|
| RERA project ID | RERA-GRG-168-2019 |
|---|
| Registration certificate number | GGM/373/105/2019/67 DATED 06.11.2019 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/01/2024 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 10.04625 acres |
|---|
| Licence | 57 of 2013 (11-07-2013) |
|---|
| Estimated cost of the project | ₹4,188 lakh (₹41.88 crore) |
|---|
| Total units (plots, apartments, shops) | 74 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 0 |
|---|
| Units unsold when registered | 75 |
|---|
| Layout plan approved on | 05-11-2015 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | Not found in the records checked |
|---|
| Revised completion date | Not found in the records checked |
|---|
| Infrastructure: projected completion | 30-07-2020 |
|---|
| Infrastructure: percentage complete when registered | 80% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/03/2024 (JAN-MAR) |
|---|
| Latest report submitted on | 15-Apr-2024 |
|---|
| Quarterly reports listed on the portal | 17 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2024 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹100.23 lakh (₹1 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹420 lakh (₹4.2 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹4.33 lakh (₹0.04 crore) |
|---|
| Units in the project (apartments / plots) | 23 plots |
|---|
| Sold in the quarter | 1 plots |
|---|
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 07-10-2015
- Demarcation Plan: Obtained Approval 28-10-2015
- Zoning Plan: Obtained Approval 05-11-2015
- Service Plans: Obtained Approval 07-10-2015
- Electricity Plans: Obtained Approval 19-10-2016
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 12 Apr 2024, for 31 Mar 2024 |
|---|
| By part | - Others: external development cost, horticulture, parks, street light or PHE (Table A): 100%, Cumulative work done value Rs 549.51 lacs
- Compliance to conditions of environment/CRZ NOC (Table A): 100%, Applicable for entire phase
- Internal roads and pavements: 100%
- Water supply: 100%
- Sewerage (chambers, lines, septic tanks): 100%
- Storm water drains: 100%
- Landscaping and tree plantation: 100%
- Street lighting/electrification: 100%
- Treatment and disposal of sewage and sullage water/STP: 100%
- Solid waste management and disposal: 100%
- Water conservation, rain water harvesting, percolating: 100%
- Electrical meter room, sub-station, receiving station: 100%
- Community centre (to be transferred to RWA): 0%
- Schools (1 high school, 1 primary): 0%
- Dispensary (1): 0%
- Creche (1): 0%
- Nursery school (2): 0%
- Taxi stand (1): 0%
- Religious building (1): 0%
- Milk and vegetable booth (2): 0%
- Nursing home (2): 0%
- Commercial building (2): 0%
|
|---|
| Unclear in the certificate | - Table A is headed as one area of 10.04625 acres (123 residential plots). No separate tower or building progress is listed.
- Sub-structure, super-structure, MEP, finishing and most installation rows are marked NA with no percentage.
- Table A MEP and external works rows have unclear column alignment; only the 0.00% figures are listed.
- Completion Certificate for the project was issued by the Town & Country Planning Department on 30-01-2024 (Memo No. LC-2755-PA(VA)-2024/3499), as noted in the certificate.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Scrutinized: 1; First Hearing: 5 |
|---|
| Proceedings | - RERA-GRG-2261-2020: The Authority's own proceeding against Experion Developers Private Limited, the promoter, under a notice issued on 05 Aug 2020. The case page does not state the reason for the proceeding. Status: Scrutinized. No next date of hearing is listed. The case page shows the first hearing as scrutinized. Latest: 14 Aug 2020, A hearing date is listed on the complaint listing. The status recorded is 'HARERA NEW COMPLAINT'. No proceedings or order text is shown.
- RERA-GRG-3314-2022: Show cause notice issued by the Authority for not submitting the quarterly progress report. The Authority asked the promoter, Experion Developers Private Limited, to explain in writing and appear at a first hearing on 27 Jun 2022. Status: First hearing listed for 27 Jun 2022. The case page shows no proceedings, bench order or order for that hearing. Latest: 27 Jun 2022, First hearing listed. The case page shows no proceedings of the day, bench order or uploaded order for this date.
- RERA-GRG-3991-2022: HARERA Gurugram proceeding (complaint RERA-GRG-3991-2022) against Experion Developers Private Limited, listed as at first-hearing stage, with a notice issued for compliance Status: At first hearing stage. The first hearing was held on 30 Jun 2022 and no order has been uploaded. Latest: 01 Jul 2022, Document received under Dak ID 36901 from the complainant side, with the remark 'NEW COMPLAINT'.
- RERA-GRG-4041-2022: The Authority's show cause notice to the promoter, Experion Developers Private Limited, for not applying to extend its registration and not submitting a completion, part completion or occupation certificate, and for not submitting the required documents. The registration certificate is shown as expired. Status: The case is listed at its first hearing, scheduled for 28 Jun 2022. No proceedings or order are recorded yet. Latest: 28 Jun 2022, First hearing scheduled. The listing shows the status as First Hearing, with no proceedings or order recorded.
- RERA-GRG-4042-2022: The Authority issued a show-cause notice to the promoter, Experion Developers Private Limited, for not completing its project within the time it declared, which the notice says breaches section 4(2)(l)(C) of the RERA Act. Status: First hearing listed for 30 Jun 2022. No proceedings of the day, bench order or order is recorded on the page yet. Latest: 30 Jun 2022, First hearing listed before the Authority. The page shows no proceedings or order for this hearing.
- RERA-GRG-4433-2022: A Project RC compliance hearing started by the Authority against the promoter, Experion Developers Private Limited, in Gurugram. The page does not explain what the RC compliance issue is. Status: First hearing listed for 01 Jul 2022. The page records no proceedings or order for that hearing. Latest: 01 Jul 2022, First hearing listed. Status shows FIRST HEARING. No proceedings of the day, bench order or order uploaded date is recorded.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 10 |
|---|
| Cases | - RERA-GRG-2323-2025 (complaint, decided 20-Jan-2026): Buyer sought delay possession charges; Authority dismissed complaint, noting part completion certificate was obtained before booking.
- RERA-GRG-2319-2025 (complaint, decided 20-Jan-2026): Buyer sought delay possession charges; HRERA dismissed complaint as not maintainable, as completion certificate was obtained before booking.
- RERA-GRG-4532-2024 (complaint, decided 08-Aug-2025): Company buyer sought possession and delay charges for a plot; HRERA ordered possession and conveyance deed but denied delay charges as no money was paid.
- RERA-GRG-2402-2024 (complaint, decided 05-Aug-2025): Buyers sought possession and delay compensation for a plot; HRERA ordered possession offered within 30 days and conveyance deed executed, with no delay interest.
- RERA-GRG-1363-2024 (complaint, decided 05-Aug-2025): Buyer sought possession and delay compensation for a plot; HRERA ordered possession offer within 30 days, but no delay interest.
- RERA-GRG-966-2024 (complaint, decided 01-Jul-2025): Allottee of a dispensary plot in The Westerlies complained of violation of Section 11(4)(a); the Member's opinion held the complaint maintainable.
- RERA-GRG-3745-2023 (complaint, decided 30-May-2025): Buyer sought delayed possession interest after plot handover; builder ordered to pay 11.10% interest for the delay from 27 Jun to 1 Sep 2021.
- RERA-GRG-1609-2023 (complaint, decided 25-Apr-2025): Buyer sought refund after cancellation; builder ordered to refund Rs 71.13 lakh after deducting 10% earnest money, with interest.
- RERA-GRG-7980-2022 (complaint, decided 25-Jan-2024): Buyer sought reinstatement of cancelled plot booking; HRERA upheld cancellation as the buyer failed to execute the agreement for sale.
- RERA-GRG-6442-2022 (complaint, decided 29-Nov-2023): Buyer's plot cancelled without signed agreement; HRERA set aside cancellation and ordered the plot restored.
|
|---|
| Decided cases against EXPERION DEVELOPERS PRIVATE LIMITED (all its projects) | 74 (Complaint: 60; Compensation: 9; Execution of an earlier order: 5) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in