Westerlies

Experion Developers · Sector 108, Gurugram

Registered with RERA: Nov 2021

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Experion Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameWESTERLIES
Builder (promoter)EXPERION DEVELOPERS PVT. LTD.
LocationSECTOR 108
RERA project IDRERA-GRG-774-2020
Registration certificate numberGGM/511/243/2021/79 DATED 15.11.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to11/09/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area16.03125 acres
Licence114/2019 Dated 12.09.2019
Estimated cost of the project₹10,487.72 lakh (₹104.88 crore)
Total units (plots, apartments, shops)194
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on22-11-2021
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction30-09-2022
Likely completion date11-09-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2024 (JAN-MAR)
Latest report submitted on15-Apr-2024
Quarterly reports listed on the portal9

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2024 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1,827.69 lakh (₹18.28 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹1,052.97 lakh (₹10.53 crore)
Project bank account (escrow): withdrawn in the quarter₹810 lakh (₹8.1 crore)
Project bank account (escrow): balance at quarter end₹409.74 lakh (₹4.1 crore)
Units in the project (apartments / plots)172 plots
Sold in the quarter8 plots
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 04-08-2020
  • Demarcation Plan: Obtained Approval 04-08-2020
  • Zoning Plan: Obtained Approval 22-11-2021
  • Service Plans: Obtained Approval 11-11-2020
  • Electricity Plans: Obtained Approval 27-04-2020

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 12 Apr 2024, for 31 Mar 2024
By part
  • Others: external development, horticulture, parks, street lights or PHE (Table A): 100%
  • Compliance to environment/CRZ NOC (entire phase): 100%
  • Internal roads and pavements: 100%
  • Water supply: 100%
  • Sewerage (chamber, lines, septic tanks): 100%
  • Storm water drains: 100%
  • Landscaping and tree plantation: 100%
  • Street lighting/electrification: 100%
  • Treatment and disposal of sewage and sullage water/STP: 100%
  • Solid waste management and disposal: 100%
  • Water conservation, rain water harvesting, percolating: 100%
  • Electrical meter room, sub-station, receiving station: 100%
  • Community centre (to be transferred to RWA): 0%
  • Schools (1 high school, 1 primary): 0%
  • Dispensary: 0%
  • Creche: 0%
  • Nursery school (2 nos.): 0%
  • Taxi stand: 0%
  • Religious building: 0%
  • Milk and vegetable booth (2 nos.): 0%
  • Nursing home (2 nos.): 0%
  • Commercial building (2 nos.): 0%
Unclear in the certificate
  • Certificate gives no separate tower or building breakdown. Table A is for the whole 10.04625 acre area (123 residential plots), and its sub-structure, super-structure, MEP and finishing rows are marked NA or 0.00.
  • Table A cumulative work value for 'Others' is 549.51 lacs, but the certificate does not state a total proposed value, so the percentage is taken as stated.
  • Project phase percentage of overall construction is not given as one figure.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed2
By statusPending: 1; Disposed: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against EXPERION DEVELOPERS PVT. LTD. (all its projects)74 (Complaint: 60; Compensation: 9; Execution of an earlier order: 5)