Projects · WHITELAND CORPORATION PRIVATE LIMITED
Whiteland Blissville
Whiteland Corporation · Sector 76, Gurugram
Registered with RERA: Aug 2022
Is it legal?
- RERA registered, valid till Jun 2027
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Dec 2026, never extended
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: 10 parts
- In progress: Waterproofing of terraces 98%, Water conservation and rain water harvesting 97%, Electrical meter room, sub-station, receiving station 97%, Internal roads and pavements 96%, Sewerage 96%, Solid waste management and disposal 96%, and 7 more
- Money: ₹481.5 crore spent of ₹538.9 crore; ₹57.4 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 220 units: 218 sold, 2 unsold (builder's certificate, July - September 2026)
- Total No of Units: 218 of 220 sold
- Total No of Plots: ? of 55 sold
- 220 units in 5 sizes, as declared to HRERA:
- 16 units of 695 sq ft carpet (4 towers)
- 40 units of 723 sq ft carpet (10 towers)
- 16 units of 884 sq ft carpet (4 towers)
- 32 units of 901 sq ft carpet (8 towers)
- 116 units of 908 sq ft carpet (29 towers)
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 18.1 km by road (47 min by car)
- Cyber City 53 min · Airport 43 min by car at 9:30 am
- Within 3 km: 2 hospitals, 1 school, 1 mall
The builder: Whiteland Corporation
- 12 projects registered in Gurugram
- 1 with an occupation certificate on record
- 1 buyer complaint decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | WHITELAND BLISSVILLE |
|---|---|
| Builder (promoter) | WHITELAND CORPORATION PRIVATE LIMITED |
| Location | SECTOR- 76 |
| RERA project ID | RERA-GRG-1117-2022 |
| Registration certificate number | GGM/604/336/2022/79 DATED 17.08.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/06/2027 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 1.9256 acres |
| Licence | 93 of 2022 Dated 12.07.2022 |
| Estimated cost of the project | ₹26,092.85 lakh (₹260.93 crore) |
| Total units (plots, apartments, shops) | 220 |
| Unit sizes (carpet area, as declared) | 16 units of 695 sq ft carpet (4 towers); 40 units of 723 sq ft carpet (10 towers); 16 units of 884 sq ft carpet (4 towers); 32 units of 901 sq ft carpet (8 towers); 116 units of 908 sq ft carpet (29 towers) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 12-07-2022 |
| Building plans approved on | 17-08-2022 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-01-2023 |
|---|---|
| Likely completion date | 31-12-2026 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 15-Oct-2026 |
| Quarterly reports listed on the portal | 16 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹4,401.98 lakh (₹44.02 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹1,401.91 lakh (₹14.02 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹2,011.17 lakh (₹20.11 crore) |
| Project bank account (escrow): deposited in the quarter | ₹4,401.98 lakh (₹44.02 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹4,563.51 lakh (₹45.64 crore) |
| Project bank account (escrow): balance at quarter end | ₹121.89 lakh (₹1.22 crore) |
| Units in the project (apartments / plots) | 220 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹749 lakh (₹7.49 crore) paid; ₹749 lakh (₹7.49 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 05 Oct 2026, for July to September 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against WHITELAND CORPORATION PRIVATE LIMITED (all its projects) | 1 (Complaint: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in