Whiteland Blissville

Whiteland Corporation · Sector 76, Gurugram

Registered with RERA: Nov 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Whiteland Corporation

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameWHITELAND BLISSVILLE
Builder (promoter)WHITELAND CORPORATION PRIVATE LIMITED
LocationSECTOR- 76
RERA project IDRERA-GRG-1201-2022
Registration certificate numberGGM/636/368/2022/111 DATED 28.11.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/06/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area1.9256 acres
Licence93 of 2022 Dated 12.07.2022
Estimated cost of the project₹27,798.67 lakh (₹277.99 crore)
Total units (plots, apartments, shops)280
Unit sizes (carpet area, as declared)8 units of 727 sq ft carpet (2 towers); 8 units of 729 sq ft carpet (2 towers); 24 units of 736 sq ft carpet (6 towers); 4 units of 875 sq ft carpet (1 tower); 4 units of 886 sq ft carpet (1 tower); 16 units of 891 sq ft carpet (4 towers); 4 units of 925 sq ft carpet (1 tower); 4 units of 926 sq ft carpet (1 tower); 28 units of 931 sq ft carpet (7 towers); 16 units of 932 sq ft carpet (4 towers); 108 units of 940 sq ft carpet (27 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on12-07-2022
Building plans approved on09-08-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-01-2023
Likely completion date31-12-2026

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal15

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹4,482.02 lakh (₹44.82 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1,427.4 lakh (₹14.27 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹2,047.73 lakh (₹20.48 crore)
Project bank account (escrow): deposited in the quarter₹4,482.01 lakh (₹44.82 crore)
Project bank account (escrow): withdrawn in the quarter₹4,646.48 lakh (₹46.46 crore)
Project bank account (escrow): balance at quarter end₹124.1 lakh (₹1.24 crore)
Units in the project (apartments / plots)224 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹763.5 lakh (₹7.64 crore) paid; ₹763.5 lakh (₹7.64 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 15-06-2022
  • Zoning Plan: Obtained Approval 05-08-2022
  • Service Plans: Obtained Approval 18-10-2022
  • Electricity Plans: Obtained Approval 18-10-2022
  • Site Plans: Obtained Approval 12-07-2022
  • Building Plans: Obtained Approval 17-08-2022
  • Fire NOC: Obtained Approval 17-05-2023

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 05 Oct 2026, for July to September 2026
By part
  • Sub structure: 100%, Excavation and raft foundation completed; basement level 1 completed; waterproofing completed
  • Super structure: 100%, Slabs, walls, staircase, lift wells and lift lobbies completed
  • Mechanical MEP: 100%, Lifts, ventilation and similar works completed
  • Electrical MEP: 100%, Conduiting, wiring and fixtures completed
  • Plumbing and firefighting MEP: 100%, Piping, pumps and pump room works completed
  • Internal finishing: 100%, Plaster, tiling, painting and similar works completed
  • External finishing: 100%, External plaster and painting completed
  • Common area flooring: 99%, Work in progress
  • Unit flooring: 99.5%, Work in progress
  • Staircase with railing: 99.5%, Work in progress
  • Doors and window panels (within units): 96%, Work in progress
  • Sanitary fixtures (within units): 65%, Work in progress
  • Modular kitchen (within units): 70%, Work in progress
  • Electrical fittings and lighting (within units): 94%, Work in progress
  • Gas piping (within units): 99%, Work in progress
  • Lifts installation: 100%, Completed
  • Overhead tanks: 96%, Work in progress
  • Underground water tank: 100%, Completed
  • Firefighting fittings and equipment as per CFO NOC: 0%, Not started
  • Electrical fittings in common areas: 75%, Work in progress
  • Compliance with environment/CRZ NOC conditions: 0%, Not started
  • Waterproofing of terraces: 96%, Work in progress
  • Entrance lobby finishing: 80%, Work in progress
  • Compound wall: 100%, Completed
  • Internal roads and pavements: 96%, Work in progress
  • Parking: 100%, Completed; covered parking marked not started but shown as 100%
  • Water supply: 93%, Work in progress
  • Sewerage (chambers, lines, septic tanks, STP): 96%, Work in progress
  • Storm water drains: 93%, Work in progress
  • Landscaping and tree plantation: 100%, Completed
  • Parks and playgrounds: 0%, Not proposed
  • Shopping area: 0%, Not proposed
  • Street lighting and electrification: 92%, Yet to be started
  • Treatment and disposal of sewage and sullage water: 96%, Yet to be started
  • Solid waste management and disposal: 96%, Yet to be started
  • Water conservation and rain water harvesting: 97%, Yet to be started
  • Energy management (solar): 0%, Yet to be started
  • Fire protection and fire safety requirements: 100%, Completed
  • Electrical meter room, sub-station, receiving station: 97%, Work in progress
Unclear in the certificate
  • Table A describes the project as 56 plots and 224 floors, and the basement level 2 entry is marked with an asterisk without explanation.
  • Table B shows covered parking as not started but gives it 100% completion.
  • No single overall percentage of completion or work done in the quarter is stated.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against WHITELAND CORPORATION PRIVATE LIMITED (all its projects)1 (Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026