Projects · EXPERION DEVELOPERS PVT. LTD
Windchants PHASE-2 ( T2, T3. S3 And S4)
Experion Developers · Sector 112, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Aug 2018 (date has passed)
- HRERA has opened 7 cases of its own against the builder over this project (7 open):
- Did not file REP-I (Part A to H) on portal for offline-registered projects (Jun 2022, open)
- Builder did not apply for registration extension, submit completion or occupation certificate, or requisite documents (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 4 more cases: reply 4
- 6 complaints about this project decided by HRERA since Nov 2023 (2 delay interest ordered, 2 refund ordered, 2 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Aug 2018, never extended (date has passed)
- 2 occupation certificates issued:
- Jul 2018: Towers T2, T12, T13, T14 and IW5 block
- Jul 2018: Towers T2, T12, T13, T14, EWS block and basement (183 flats)
- Construction, as certified by the architect (Jul–Sep 2026):
- Money: ₹259.3 crore spent of ₹259.3 crore (CA certificate, Sep 2026)
What's on offer?
- 171 units, as declared to HRERA:
- 110 units averaging about 1,600 sq ft carpet (1 tower)
- 48 units averaging about 2,530 sq ft carpet (1 tower)
- 7 units averaging about 3,430 sq ft carpet (1 tower)
- 6 units averaging about 3,630 sq ft carpet (1 tower)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 5.8 km by road (11 min by car)
- Cyber City 50 min · Airport 29 min by car at 9:30 am
- Within 3 km: 7 hospitals, 1 school, 1 mall
The builder: Experion Developers
- 16 projects registered in Gurugram, 3 lapsed
- 6 with an occupation certificate on record
- 74 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | WINDCHANTS PHASE-2 ( T2, T3. S3 AND S4) |
|---|
| Builder (promoter) | EXPERION DEVELOPERS PVT. LTD |
|---|
| Location | SECTOR-112, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-1147-2022 |
|---|
| Registration certificate number | 64 OF 2017 DATED 18.8.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 17/08/2018 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|
| Land area | 2.442 acres |
|---|
| Licence | Licence No 21 of 2008, Licence no 28 of 2012 |
|---|
| Estimated cost of the project | ₹25,932 lakh (₹259.32 crore) |
|---|
| Total units (plots, apartments, shops) | 171 |
|---|
| Unit sizes (carpet area, as declared) | 110 units averaging about 1,600 sq ft carpet (1 tower); 48 units averaging about 2,530 sq ft carpet (1 tower); 7 units averaging about 3,430 sq ft carpet (1 tower); 6 units averaging about 3,630 sq ft carpet (1 tower) |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | Not applicable (new project) |
|---|
| Units unsold when registered | Not applicable (new project) |
|---|
| Layout plan approved on | 07-06-2012 |
|---|
| Building plans approved on | 07-06-2012 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 13-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 32 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹5.2 lakh (₹0.05 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹27.34 lakh (₹0.27 crore) |
|---|
| Units in the project (apartments / plots) | 171 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹983 lakh (₹9.83 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 07-06-2012
- Demarcation Plan: Obtained Approval 07-06-2012
- Zoning Plan: Obtained Approval 07-06-2012
- Service Plans: Obtained Approval 23-10-2012
- Electricity Plans: Obtained Approval 07-06-2012
- Site Plans: Obtained Approval 07-06-2012
- Building Plans: Obtained Approval 07-06-2012
- Fire NOC: Obtained Approval 23-07-2018
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 07 Oct 2026, for 30 Sep 2026 |
|---|
| By part | - Tower T2: 100%, G+27 floor slabs all completed; sub-structure, super-structure, MEP, internal and external finishing all certified at 100%
|
|---|
| Unclear in the certificate | - Table B says 'Ground Floor Only' for total floors in the tower, but also says G+27 floor slabs are all completed. These entries conflict.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Occupation Certificate (Form BR.VII): covers Group Housing Colony in Sector-112, Gurugram. Tower T2 (stilt/ground floor to 11th floor, 110 dwelling units), Tower T12 (stilt/ground floor to 27th floor, 48 dwelling units), Tower T13 (stilt/ground floor to 7th floor, 6 dwelling units), Tower T14 (stilt/ground floor to 14th floor, 7 dwelling units), IW5 block (ground floor to 3rd floor), and Basement-1 (non-FAR area 9282.385 sq m).. Addressed to Experion Developers Pvt Ltd. and others. Composition fees for variations from approved plans: ₹38,88,770. Unclear in the document: Memo date is garbled in the document, so the issue date could not be read.; Floor limits for Tower T2 (11th), Tower T12 (27th) and Tower T14 (14th) are partly garbled and read with uncertainty.; Composition fee reads as 38,88,77 followed by garbled digits; last digit taken as 0 and may be inaccurate.; IW5 block dwelling unit figures (100 and 12) are unclear, so the total number of dwelling units could not be confirmed.; Occupation certificate application date of 16.01.2018 is stated in the document but not used as the issue date.
- Occupation Certificate (Form BR-VII) dated 23 Jul 2018: covers Group Housing Colony measuring 23.431 acres in Sector-112, Gurugram, under Licence no. 21 of 2008 and Licence no. 28 of 2012. Covers Tower-T2 (stilt/ground to 27th floor), Tower-T12 (stilt/ground to 27th floor), Tower-T13 (stilt/ground to 7th floor), Tower-T14 (stilt/ground to 7th floor), the EWS Block (ground to 3rd floor) and Basement-1.. Addressed to Experion Developers Pvt. Ltd. and others. Composition fees for variations from approved plans: ₹38,88,774. Unclear in the document: The table lists 271 dwelling units as sanctioned (EWS block 100 sanctioned, 12 constructed) but 183 dwelling units in the 'No. of Dwelling Units' column; 183 is used here.
|
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 7 |
|---|
| By status | First Hearing: 5; Online Complaint Not Yet Received At Office: 1; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2684-2022: The Authority's own proceeding against the promoter, Experion Developers Pvt. Ltd, for not filing REP-I (Part A to H) on the Authority's web portal for offline registered projects, either with the Interim Real Estate Regulatory Authority, Panchkula, or HRERA Gurugram. Status: First hearing listed for 29 Jun 2022. The listing shows the status as FIRST HEARING, with no order uploaded. Latest: 29 Jun 2022, First hearing was listed at 11:00 am at HARERA Gurugram. The notice asked the promoter to appear if it had anything to say in the matter.
- RERA-GRG-2702-2022: Complaint RERA-GRG-2702-2022, with HARERA Gurugram shown as the complainant against Experion Developers Pvt. Ltd. The page does not state what the complaint is about. Status: The page shows the online complaint as not yet received at the office. Complaint dispatch is shown as not yet done, and no next hearing date is listed.
- RERA-GRG-2876-2022: The Authority issued a show cause notice to the promoter, Experion Developers Pvt. Ltd., for not applying for extension of registration and for not submitting a completion certificate, part completion certificate or occupation certificate, and for not submitting requisite documents. The case page lists the registration certificate as expired. Status: First hearing stage. The next hearing is listed for 28 Jun 2022. No order has been uploaded and no proceedings are recorded for the day. Latest: 28 Jun 2022, First hearing listed. The case page shows the status as 'First Hearing' with no proceedings or bench order recorded.
- RERA-GRG-2877-2022: Show-cause notice by the Authority (HARERA Gurugram) to the promoter Experion Developers Pvt. Ltd. for not adhering to the time period it declared for completing the project, under section 4(2)(l)(C) of the RERA Act. Status: First hearing listed for 30 Jun 2022. The case page shows the status as FIRST HEARING, with no proceedings, bench order or order recorded yet. Latest: 30 Jun 2022, First hearing listed. No proceedings or order are recorded for this date.
- RERA-GRG-2935-2022: Show cause notice issued by the Authority to the promoter, Experion Developers Pvt. Ltd, for not submitting a quarterly progress report. The case was started by the Authority itself. Status: First hearing listed for 27 Jun 2022. The page shows no proceedings or order from that hearing. Latest: 27 Jun 2022, First hearing listed. The status is recorded as 'First Hearing' with no proceedings of the day, bench order or uploaded order shown.
- RERA-GRG-5096-2022: A complaint numbered RERA-GRG-5096-2022, filed in the name of the Authority through a representative against Experion Developers Pvt. Ltd. The page does not state the nature of the grievance. Status: First hearing stage. The page lists the first hearing for 30 Jun 2022, and the listing shows no proceedings or order for that day. Latest: 16 Jul 2022, A document was received from the Authority's representative, marked as a new complaint. This date is after the listed hearing date.
- RERA-GRG-5254-2019: The Authority started this proceeding against the promoter, Experion Developers Pvt. Ltd., for the Windchants Phase-2 group housing project in Sector 112, Gurugram. The promoter had not filed the online and hard copy REP-I (Part A to H) project updates and quarterly progress reports for a project that was registered offline. Status: Pending. The case page shows the status as PENDING. The next hearing date listed is 24 Feb 2020, and a third notice was dispatched on 20 Jul 2020. No final decision appears in these documents. Latest: 20 Jul 2020, Third notice dispatched to the promoter, concerning the section 42 (1D) requirement. Penalty: Rs 25,000 per day from 31 Dec 2019 while the default continues, cumulatively up to five percent of the estimated cost of the real estate project as determined by the Authority. The order states the Authority decided to impose this penalty.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 6 |
|---|
| Cases | |
|---|
| Decided cases against EXPERION DEVELOPERS PVT. LTD (all its projects) | 74 (Complaint: 60; Compensation: 9; Execution of an earlier order: 5) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in