Projects · EXPERION DEVELOPERS PVT LTD
Windchants Phase 3
Experion Developers · Sector 112, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Aug 2020 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit quarterly progress report (May 2022, open)
- Did not submit completion, part completion or occupation certificate after extension lapsed (Jun 2022, open)
- Submitted REP-I Part (A-H) on HARERA website; Authority ordered scrutiny and corrections (Nov 2019, open)
- 3 more cases: reply 4
Will it be delivered on time?
- Deadline Aug 2020, never extended (date has passed)
- 5 occupation certificates issued:
- Dec 2018: Towers T7, T8, villas, townhouses, EWS part, 9 shops (128 flats)
- Dec 2018: Towers T7, T8, villas, townhouses, part EWS block, shops (128 flats)
- Mar 2022: Four towers, three villas and nine townhouses (40 flats)
- Aug 2022: Towers T6, T9, T10 and T11 only (27 flats)
- Construction, as certified by the architect (Jul–Sep 2026):
- Money: ₹440.1 crore spent of ₹445.3 crore (CA certificate, Sep 2026)
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 5.9 km by road (12 min by car)
- Cyber City 51 min · Airport 30 min by car at 9:30 am
- Within 3 km: 7 hospitals, 1 school, 1 mall
The builder: Experion Developers
- 16 projects registered in Gurugram, 3 lapsed
- 6 with an occupation certificate on record
- 74 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | WINDCHANTS PHASE 3 |
|---|
| Builder (promoter) | EXPERION DEVELOPERS PVT LTD |
|---|
| Location | SECTOR 112, CHOMA, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-392-2019 |
|---|
| Registration certificate number | 73 OF 2017 DATED 21.08.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 20/08/2020 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 11.189 acres |
|---|
| Licence | Licence No 21 of 2008, Licence no 28 of 2012 |
|---|
| Estimated cost of the project | ₹44,527 lakh (₹445.27 crore) |
|---|
| Total units (plots, apartments, shops) | 180 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 65 |
|---|
| Units unsold when registered | 115 |
|---|
| Layout plan approved on | 21-08-2017 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 20-08-2019 |
|---|
| Revised completion date | 20-08-2020 |
|---|
| Infrastructure: projected completion | 20-08-2020 |
|---|
| Infrastructure: percentage complete when registered | 100% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 13-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 32 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹5.2 lakh (₹0.05 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹27.34 lakh (₹0.27 crore) |
|---|
| Units in the project (apartments / plots) | 180 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹2,265.46 lakh (₹22.65 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 07-06-2012
- Demarcation Plan: Obtained Approval 07-06-2012
- Zoning Plan: Obtained Approval 07-06-2012
- Service Plans: Obtained Approval 07-06-2012
- Electricity Plans: Obtained Approval 07-06-2012
- Site Plans: Obtained Approval 07-06-2012
- Building Plans: Obtained Approval 07-04-2012
- Fire NOC: Obtained Approval 09-03-2022
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 07 Oct 2026, for 30 Sep 2026 |
|---|
| By part | - Tower T4: 100%, All slabs of G+27 floors completed; all listed sub-structure, super-structure, MEP and finishing items shown at 100%
- Tower T5: 100%, Sub-structure, super-structure, MEP and internal finishing shown at 100%
|
|---|
| Unclear in the certificate | - Tower T4 sheet says 'Total floors: Ground Floor Only' but also says 'G+27 Floors, All Completed' for slabs; the certificate does not clarify this.
- Tower T4 sheet has 'Basement level 2*' with an asterisk, but no footnote explains it.
- Tower T5 table lists only sub-structure, super-structure, MEP and internal finishing; external finishing and the floor-wise status tables are not shown for this tower.
- Work done during the quarter is left blank in both tower tables, so quarter progress cannot be read.
- Overall percentage for the whole project is not stated as one figure.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Occupation Certificate (Form BR-VII) dated 24 Dec 2018: covers Group Housing Colony in Sector 112, Gurugram: Tower T7 and T8 (96 dwelling units, stilt/ground floor to 27th floor); Villas V2, V3 and V5A (3 units, ground to 2nd floor); Townhouses TH-2, TH-3, TH-12, TH-12A and TH-14 (5 units, ground to 2nd floor); EWS Block (part) (24 units, ground to 3rd floor); Convenient Shopping (9 shops, ground floor only).. Addressed to Experion Developers Pvt. Ltd. and others. Composition fees for variations from approved plans: ₹21,00,635. Unclear in the document: The document contains a second Occupation Certificate (Form BR-VII), dated 09 Mar 2022, for Towers T3, T4, T16 and T17, villas, townhouses and 40 main dwelling units, with composition charges of Rs 21,37,596. The fields above reflect only the first certificate dated 24 Dec 2018.; The EWS Block (part) row shows achieved FAR of 581.48 sq m against 2274.137 sq m sanctioned, and the table total for achieved area (34628.326) does not clearly match the row figures; figures are reported as printed.
- Occupation Certificate (Form BR-VII) dated 24 Dec 2018: covers Group Housing Colony in Sector 112, Gurugram (licences 21 of 2008 and 28 of 2012). Covers Towers T7 and T8 (96 dwelling units, stilt/ground floor to 27th floor); Villas V2, V3 and V5A (3 units, ground to 2nd floor); Townhouses TH-2, TH-3, TH-12, TH-12A and TH-14 (5 units, ground to 2nd floor); part of EWS Block (24 units, ground to 3rd floor); and Convenient Shopping (9 shops, ground floor only). Also covers the 1st basement and basements in townhouses. Total 128 dwelling units.. Addressed to Experion Developers Pvt. Ltd. and others. Composition fees for variations from approved plans: ₹21,00,635. Unclear in the document: The endorsement date on page 3 is left blank.
- Occupation Certificate (Form BR-VII), Memo No. ZP-595-Vol.-II/AD(RA)/2018/34668 dated 24 Dec 2018: covers Towers T7 and T8 (96 dwelling units), Villas V2, V3 and V5A (3 units), Townhouses TH-2, TH-3, TH-12, TH-12A and TH-14 (5 units), part of the EWS Block (24 units), and the Convenient Shopping block with 9 shops on the ground floor. Also covers the 1st basement and the basements in the townhouses. Stilt/ground floor to 27th floor for the towers.. Addressed to Experion Developers Pvt. Ltd. and others. Composition fees for variations from approved plans: ₹21,00,635. Unclear in the document: The same PDF also contains a second Occupation Certificate (Memo No. ZP-595-Vol-II/SD(DK)/2022/6339, dated 09 Mar 2022, issued to Experion Developers Pvt. Ltd.) covering Towers T3, T4, T16 and T17, villas V1, V4 and V5, and townhouses TH1 and TH4 to TH11 with 40 main dwelling units and composition charges of Rs 21,37,596. This is not summarised in the fields above.; The EWS Block is described only as '(part)' in the table, so the exact portion covered is not stated.
- Occupation Certificate (Form BR-VII) dated 09 Mar 2022: covers Group Housing Colony measuring 23.431 acres in Sector-112, Gurugram Manesar Urban Complex: Towers T3, T4, T16 and T17 (ground to 7th floor, 7 dwelling units each); Villas V1, V4 and V5 (ground to 2nd floor, 1 unit each); Townhouses TH1 and TH4 to TH11 (ground to 2nd floor, 1 unit each); with their basements and stilts. Total 40 main dwelling units.. Addressed to Experion Developers Pvt. Ltd.. Composition fees for variations from approved plans: ₹21,37,596
- Occupation Certificate (Form BR-VII) dated 29 Aug 2022: covers Towers T6 (Type-D), T9 (Type-D), T10 (Type-C) and T11 (Type-E) in the Group Housing Colony measuring 23.431 acres, Sector-112, Gurugram Manesar Urban Complex. Each tower covers Ground Floor to 7th Floor. Also covers mumty areas on these towers.. Addressed to Experion Developers Pvt. Ltd.. Composition fees for variations from approved plans: ₹4,94,51,932. Unclear in the document: Page 4 order refers to a separate occupation certificate (memo 6339 dated 09.03.2022) for Towers T3, T4, T16, T17, villas, townhouses and basement. That certificate is not part of this document's coverage.; Page 4 order records a separate compounding fee of Rs 1,00,000 for delay in filing the deed of declaration. This is not the composition charge for plan variations.
|
|---|
| Corrigenda / addenda to the registration | - Extension of Registration Certificate (Extension No. 02 of 2020), not a corrigendum or addendum. It extends the registration granted vide no. 2017/73 revised as 2020/02 for Real Estate Project Windchants Phase-3. dated 20 Jan 2020: The Authority extended the registration of Windchants Phase-3, Sector-112, Gurugram, for nine months, valid till 20 Aug 2020. Registration number is RC/REP/HARERA/GGM/2017/73. Project details: total licensed area 23.431 acres; area for registration 11.189 acres (45281.883 sq mtrs); nature Group Housing; total FAR of the phase registered 63005.94 sq mtrs; 10 towers, 14 townhouses, 6 villas and 9 retail shops; 151 apartments, 14 townhouses, 6 villas and 9 retail shops (180 units in total). Promoter 1 (license holder) is KNS Nirman Private Limited. Promoter 2 (collaborator and developer) is Experion Developers Private Limited. Conditions: renew environmental clearance within 3 months of issue; submit a copy of the occupation certificate when received; offer to execute and register conveyance deeds for allottees; deposit 70 percent of amounts realised in a separate schedule bank account for construction and land cost; comply with the Act and rules; and not contravene any other applicable law. If conditions are not met, the Authority may revoke the registration.
|
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 2; First Hearing: 3; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2711-2022: Complaint RERA-GRG-2711-2022 listed as HARERA Gurugram, through a representative, versus Experion Developers Pvt Ltd. The page does not state the subject matter of the complaint. Status: Online complaint not yet received at office. Complaint not yet dispatched. No next hearing date listed (NA).
- RERA-GRG-2954-2022: The Authority issued a show cause notice to Experion Developers Pvt Ltd for not submitting its quarterly progress report. Case RERA-GRG-2954-2022 is listed for first hearing on 27 Jun 2022. Status: First hearing listed for 27 Jun 2022. The page shows status 'First Hearing', no proceedings recorded for the day, and no order uploaded. Latest: 27 Jun 2022, First hearing scheduled at 11.00 am at the HARERA Gurugram office, New PWD Rest House, Civil Lines, Gurugram.
- RERA-GRG-3737-2022: The Authority started this proceeding against Experion Developers Pvt Ltd because it had not submitted a completion certificate, part completion certificate or occupation certificate, even after the validity of its registration extension had lapsed. The Authority is asked to take up the submission of the required documents. Status: First hearing listed for 11 Jul 2022. The case page shows no proceedings or order for that hearing. The registration extension status is shown as expired. Latest: 11 Jul 2022, First hearing listed. The status is recorded as First Hearing, with no proceedings of the day, bench order or order uploaded.
- RERA-GRG-3741-2022: The Authority's proceeding RERA-GRG-3741-2022 against Experion Developers Pvt Ltd, the promoter. The case page does not state the reason for the proceeding. Status: Case page shows 'Online complaint not yet received at office'. Next date of hearing is NA. Complaint dispatch is 'Not Yet'. No hearing listings or orders are shown.
- RERA-GRG-5109-2022: A case listed as RERA-GRG-5109-2022, titled HARERA Gurugram through an official versus Experion Developers Pvt Ltd. The page does not state the grievance or the reason for the case. Status: At first hearing stage. The first hearing was listed for 30 Jun 2022, no proceedings or order are recorded, and no order has been uploaded. Latest: 16 Jul 2022, A document was received under dak ID 37974, submitted by the party listed as 'Asha', with the remark 'NEW COMPLAINT'.
- RERA-GRG-5262-2019: Filing of the REP-I Part (A-H) on the HARERA website for the registered project 'Windchants' Phase 3 in Sector-112, Gurugram, developed by M/s Experion Developers Pvt. Ltd. The Authority directed scrutiny of the REP-I Part (A-H) submitted by the promoter, with deficiencies to be corrected online and hard copies submitted before the next hearing. Status: Pending. The case page shows the case as PENDING with the next hearing date listed as 17 Feb 2020. Latest: 20 Jul 2020, Third notice dispatched to the promoter under section 42(1D). The case page also shows the complaint as dispatched on this date.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|
| Decided cases against EXPERION DEVELOPERS PVT LTD (all its projects) | 74 (Complaint: 60; Compensation: 9; Execution of an earlier order: 5) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in