Projects · ORRIS INFRASTRUCTURE PRIVATE LIMITED
Woodview Residencies
Orris Infrastructure · Sector 89, Gurugram
Registered with RERA: Oct 2020
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jul 2023)
- HRERA has opened 3 cases of its own against the builder over this project (3 open):
- Did not submit a quarterly progress report (May 2022, open)
- 2 more cases: reply 4
- 25 complaints about this project decided by HRERA since Nov 2023 (3 delay interest ordered, 17 refund ordered, 5 dismissed, withdrawn or settled)
Will it be delivered on time?
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Apr–Jun 2026):
- Done: 12 parts
- In progress: Fire protection and fire safety requirements 40%
- Money: ₹352.5 crore spent of ₹397.1 crore; ₹44.6 crore still to spend (CA certificate, Jun 2026)
Location
- Nearest metro: Millennium City Centre Gurugram, 20.9 km by road (54 min by car)
- Cyber City 60 min · Airport 45 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Orris Infrastructure
- 4 projects registered in Gurugram, 3 lapsed
- 0 with an occupation certificate on record
- 125 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | WOODVIEW RESIDENCIES |
|---|
| Builder (promoter) | ORRIS INFRASTRUCTURE PRIVATE LIMITED |
|---|
| Location | SECTOR 89-90, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-640-2020 |
|---|
| Registration certificate number | GGM/418/150/2020/34 DATED 06.10.2020 |
|---|
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 15/07/2023 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 114.506 acres |
|---|
| Licence | 59 of 2013 and 115 0f 2019 |
|---|
| Estimated cost of the project | ₹39,709.75 lakh (₹397.1 crore) |
|---|
| Total units (plots, apartments, shops) | 0 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 0 |
|---|
| Units unsold when registered | 0 |
|---|
| Layout plan approved on | 02-08-2019 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | Not found in the records checked |
|---|
| Revised completion date | Not found in the records checked |
|---|
| Infrastructure: projected completion | 15-07-2023 |
|---|
| Infrastructure: percentage complete when registered | 0% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/06/2026 (APR-JUN) |
|---|
| Latest report submitted on | 13-Aug-2026 |
|---|
| Quarterly reports listed on the portal | 22 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹58.92 lakh (₹0.59 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 576 plots |
|---|
| Sold in the quarter | Not found in the records checked |
|---|
| EDC (development charges): paid / due as on date | ₹6,973.93 lakh (₹69.74 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 02-08-2019
- Demarcation Plan: Obtained Approval 21-09-2021
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 10 Jul 2026, for 30 Jun 2026 |
|---|
| By part | - Internal roads & pavements: 100%
- Water supply: 100%
- Sewerage (chamber, lines, septic tanks, STP): 100%
- Storm water drains: 100%
- Landscaping & tree plantation: 100%
- Parks and playgrounds: 100%
- Benches: 100%
- Street lighting/ electrification: 100%
- Treatment and disposal of sewage and sullage water/ STP: 100%
- Water conservation, rain water harvesting, percolating well/ pit: 100%
- Fire protection and fire safety requirements: 40%
- Electrical meter room, sub-station, receiving station: 100%
- U.G. Tank: 100%
|
|---|
| Unclear in the certificate | - Table A (building/tower-wise progress: sub-structure, super-structure, MEP, finishing) is marked NA for every item, so no tower-wise percentages are given.
- The figure 100% beside 'Date of certifying of percentage of construction work/site inspection' is not clearly an overall completion figure, so no overall percentage is recorded.
- No individual tower or block names are listed in the certificate.
- Table B items marked without a percentage (children play equipment, shopping area, schools, dispensary, club, parking) have no progress figure stated.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 3 |
|---|
| By status | First Hearing: 3 |
|---|
| Proceedings | - RERA-GRG-3449-2022: The Authority issued a show cause notice to the promoter, Orris Infrastructure Private Limited, for not submitting a quarterly progress report. The notice asks the promoter to appear at a first hearing on 27 Jun 2022 and give a written reply if it has anything to say. Status: First hearing listed for 27 Jun 2022. No proceedings or order are recorded on the case page. Latest: 27 Jun 2022, First hearing was listed. The case page shows no proceedings of the day and no order uploaded.
- RERA-GRG-4082-2022: Proceedings in complaint RERA-GRG-4082-2022, listed as HARERA Gurugram (through its representative) against Orris Infrastructure Private Limited. The page shows a first hearing on 30 Jun 2022, with a compliance notice dispatched on 03 Jun 2022. Status: First hearing listed for 30 Jun 2022. The page shows no proceedings of the day, no bench order and no uploaded order for that date. Latest: 30 Jun 2022, First hearing listed in the case. Documents were received under dak ID 36779, with the remark 'NEW COMPLAINT'.
- RERA-GRG-4356-2022: Case RERA-GRG-4356-2022, listed as HARERA Gurugram against Orris Infrastructure Private Limited, about a project RC compliance hearing. The page does not state the specific compliance breach. Status: First hearing listed for 01 Jul 2022. The page shows the status as FIRST HEARING, with the next hearing date also shown as 01 Jul 2022. Latest: 01 Jul 2022, First hearing was listed. The proceedings, bench and order fields are blank ('---').
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 25 |
|---|
| Cases | - RERA-GRG-169-2025 (compensation, decided 13-Apr-2026): Buyer sought compensation after unit was not allotted; authority dismissed complaint as buyer was not an allottee.
- RERA-GRG-4361-2024 (complaint, decided 29-Jan-2026): Buyer sought plot allotment, agreement and possession; HRERA dismissed the complaint for lack of proof of allotment.
- RERA-GRG-4765-2024 (complaint, decided 23-Dec-2025): Buyer sought refund after possession was not handed over; settlement from 2022 found binding, so complaint disposed of.
- RERA-GRG-6295-2024 (complaint, decided 16-Dec-2025): Investor sought possession and delay charges on a 2011 plot agreement; HRERA dismissed it as not an allottee complaint.
- RERA-GRG-2339-2024 (complaint, decided 12-Sep-2025): Buyer sought delay possession interest for late unit; HRERA ordered builder to pay 10.85% interest on amount paid and execute conveyance deed.
- RERA-GRG-1711-2024 (compensation, decided 05-Sep-2025): Buyers sought compensation for delayed possession; builder ordered to pay Rs 10.10 lakh plus 10.50% interest.
- RERA-GRG-2669-2024 (complaint, decided 08-Aug-2025): Buyer sought Rs 12.07 lakh refund plus interest; HRERA dismissed it, noting full refund already accepted and agreement cancelled.
- RERA-GRG-3812-2023 (complaint, decided 22-May-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 26.08 lakh with 11.10% interest in 90 days.
- RERA-GRG-762-2023 (complaint, decided 16-May-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 1.23 crore with 11.10% interest.
- RERA-GRG-791-2023 (complaint, decided 16-May-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 1.23 crore with 11.10% interest.
- RERA-GRG-746-2023 (complaint, decided 16-May-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 1.23 crore with 11.10% interest.
- RERA-GRG-3698-2023 (complaint, decided 16-May-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 1.23 crore with 11.10% interest.
- RERA-GRG-797-2023 (complaint, decided 16-May-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 1.23 crore with 11.10% interest.
- RERA-GRG-4906-2023 (complaint, decided 16-May-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 1.23 crore with 11.10% interest.
- RERA-GRG-773-2023 (complaint, decided 16-May-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 1.23 crore with 11.10% interest.
- RERA-GRG-748-2023 (complaint, decided 16-May-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 1.23 crore with 11.10% interest.
- RERA-GRG-745-2023 (complaint, decided 16-May-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 1.23 crore with 11.10% interest.
- RERA-GRG-5583-2023 (complaint, decided 27-Feb-2025): Buyers sought refund after possession delay; builder ordered to refund Rs 47.85 lakh with 11.10% interest.
- RERA-GRG-83-2024 (complaint, decided 13-Feb-2025): Buyers sought delay interest and compensation; HRERA ordered builder to pay 11.10% delay interest on Rs 79.26 lakh.
- RERA-GRG-898-2024 (complaint, decided 13-Sep-2024): Buyers sought refund after possession delay; builder ordered to refund Rs 34.84 lakh with 11.10% interest
- RERA-GRG-900-2024 (complaint, decided 13-Sep-2024): Buyer sought refund after possession was not given; builder ordered to refund Rs 24.31 lakh with 11.10% interest
- RERA-GRG-956-2023 (complaint, decided 21-Aug-2024): Buyers sought refund after possession delay; builder ordered to refund Rs 58.38 lakh with 11.10% interest.
- RERA-GRG-4405-2023 (complaint, decided 16-Aug-2024): Buyer sought refund after possession delay; builder ordered to refund Rs 29.56 lakh with 11.10% interest.
- RERA-GRG-6501-2022 (complaint, decided 02-Feb-2024): Buyer sought refund after 4-year possession delay; builder ordered to refund Rs 1.51 crore with 10.85% interest.
- RERA-GRG-2042-2022 (complaint, decided 15-Dec-2023): Buyer sought refund after possession delay; HRERA ordered builder to refund Rs 31.8 lakh less 10% earnest money, with 10.75% interest.
|
|---|
| Decided cases against ORRIS INFRASTRUCTURE PRIVATE LIMITED (all its projects) | 125 (Complaint: 100; Execution of an earlier order: 12; Compensation: 13) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in