Projects · APRICUS HILLS PRIVATE LIMITED

YASHIKA-104

Apricus Hills · Sector 104, Gurugram

Registered with RERA: May 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Apricus Hills

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameYASHIKA-104
Builder (promoter)APRICUS HILLS PRIVATE LIMITED
LocationVILLAGE DHANWAPUR, SECTOR-104 , GURUGRAM
RERA project IDRERA-GRG-1047-2022
Registration certificate numberGGM/569/301/2022/44 DATED 25.05.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to06/01/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.0375 acres
Licence101 of 2021
Estimated cost of the project₹22,192.99 lakh (₹221.93 crore)
Total units (plots, apartments, shops)754
Unit sizes (carpet area, as declared)50 units averaging about 490 sq ft carpet (2 towers); 704 units averaging about 600 sq ft carpet (7 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on04-03-2022
Building plans approved on04-03-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2022
Likely completion date14-06-2027

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on08-Nov-2026
Quarterly reports listed on the portal17

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹345.5 lakh (₹3.46 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹69 lakh (₹0.69 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹81.45 lakh (₹0.81 crore)
Project bank account (escrow): deposited in the quarter₹241.85 lakh (₹2.42 crore)
Project bank account (escrow): withdrawn in the quarter₹241.85 lakh (₹2.42 crore)
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)830 apartments
Sold in the quarter14 apartments
EDC (development charges): paid / due as on date₹582.08 lakh (₹5.82 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 19-10-2021
  • Zoning Plan: Obtained Approval 08-12-2021
  • Service Plans: Obtained Approval 10-03-2022
  • Electricity Plans: Obtained Approval 16-12-2021
  • Site Plans: Obtained Approval 04-03-2022
  • Building Plans: Obtained Approval 04-03-2022
  • Fire NOC: Obtained Approval 04-10-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026
By part
  • Sub structure: 80%, Work done in quarter 4%; cumulative work done till date 76%
  • Super structure: 52%, Work done in quarter 4%; cumulative work done till date 48%
  • Mechanical (lifts, ventilation): 38%, Work done in quarter 12%; cumulative work done till date 26%
  • Electrical (conduiting, wiring, fixtures): 35%, Work done in quarter 15%; cumulative work done till date 20%
  • Plumbing & Firefighting (piping, pumps, fixtures): 42%, Work done in quarter 11%; cumulative work done till date 31%
  • Finishing - Internal (plaster, tiling, flooring, painting): 39%, Work done in quarter 20%; cumulative work done till date 19%
  • Finishing - External (plaster, painting, facade): 27%, Work done in quarter 5%; cumulative work done till date 22%
  • Internal roads & pavements: 45%
  • Parking: 40%
  • Water supply: 12%
  • Sewerage (chamber, lines, septic tanks, STP): 55%
  • Storm water drains: 35%
  • Landscaping & tree plantation: 15%
  • Parks and playgrounds: 0%
  • Fixing of children play equipment: 0%
  • Benches: 0%
  • Shopping area: 45%
  • Street lighting/ electrification: 10%
  • Treatment and disposal of sewage and sullage water/ STP: 12%
  • Solid waste management & disposal: 20%
  • Water conservation, rain water harvesting, percolating well/ pit: 30%
  • Energy management (solar): 0%
  • Fire protection and fire safety requirements: 15%
  • Electrical meter room, sub-station, receiving station: 35%
  • Other (option to add more) - B-1: 50%
  • Community centre: 5%
  • Others - B-3 (community buildings not to be transferred): 60%
Unclear in the certificate
  • The certificate does not state the quarter it reports on.
  • The certificate gives no single overall percentage of construction complete or of work done in the quarter; only figures by component are given.
  • The certificate is dated 30.09.2026 but states the last site inspection date as 03.10.2026, which is after the certificate date.
  • The table of services to be transferred to the competent authority (B-4) has no entries.
  • The percentage column for 'Percentage of work done to the total proposed work' and the 'cumulative work done value till date' column differ; the certificate does not say which one is the overall progress figure, so both are noted.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusPending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project4
Cases
Decided cases against APRICUS HILLS PRIVATE LIMITED (all its projects)12 (Complaint: 12)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in