Projects · DISHITA INFRA PVT. LTD.
Yashika Green Square
Dishita Infra · Sector 99A, Gurugram
Registered with RERA: Jul 2023
Is it legal?
- RERA registered, valid till Jan 2028
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Jan 2028, never extended
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- In progress: Sub structure 58%, Mechanical 15%, Internal finishing 15%, Electrical 12%, Fire protection and fire safety requirements 10%, Electrical meter room, sub-station, receiving station 10%, and 18 more
- Money: ₹98 crore spent of ₹170.3 crore; ₹72.3 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 590 units in 5 sizes, as declared to HRERA:
- 32 units of 307 sq ft carpet (7 towers)
- 112 units of 561 sq ft carpet (7 towers)
- 28 units of 576 sq ft carpet (7 towers)
- 84 units of 584 sq ft carpet (7 towers)
- 334 units of 646 sq ft carpet
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: IFFCO Chowk, 16.4 km by road (48 min by car)
- Cyber City 57 min · Airport 37 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 1 mall
The builder: Dishita Infra
- 1 project registered in Gurugram
- 0 with an occupation certificate on record
- 1 buyer complaint decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | YASHIKA GREEN SQUARE |
|---|---|
| Builder (promoter) | DISHITA INFRA PVT. LTD. |
| Location | SECTOR-99A, VILLAGE GOPALPUR, GURURGAM |
| RERA project ID | RERA-GRG-1386-2023 |
| Registration certificate number | GGM/737/469/2023/81 DATED 24.07.2023 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/01/2028 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 4.2500 acres |
| Licence | Licence No. 32 of 2023 dated 14.02.2023 Department of Town and Country Planning, Haryana |
| Estimated cost of the project | ₹17,030.77 lakh (₹170.31 crore) |
| Total units (plots, apartments, shops) | 590 |
| Unit sizes (carpet area, as declared) | 32 units of 307 sq ft carpet (7 towers); 112 units of 561 sq ft carpet (7 towers); 28 units of 576 sq ft carpet (7 towers); 84 units of 584 sq ft carpet (7 towers); 334 units of 646 sq ft carpet |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 07-07-2023 |
| Building plans approved on | 07-07-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-04-2023 |
|---|---|
| Likely completion date | 31-01-2028 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 13-Nov-2026 |
| Quarterly reports listed on the portal | 12 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹1,528.24 lakh (₹15.28 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹482.09 lakh (₹4.82 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹857.67 lakh (₹8.58 crore) |
| Project bank account (escrow): deposited in the quarter | ₹1,227.35 lakh (₹12.27 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹1,185 lakh (₹11.85 crore) |
| Project bank account (escrow): balance at quarter end | ₹57.81 lakh (₹0.58 crore) |
| Units in the project (apartments / plots) | 682 apartments |
| Sold in the quarter | 3 apartments |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against DISHITA INFRA PVT. LTD. (all its projects) | 1 (Complaint: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in