Projects · EXPERION DEVELOPERS PVT LTD
Zephyr At The Westerlies
Experion Developers · Sector 108, Gurugram
Registered with RERA: Jun 2020
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jul 2024)
- HRERA has opened 3 cases of its own against the builder over this project (3 open):
- Did not submit a quarterly progress report to the Authority (May 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Aug 2025, open)
- 1 more case: reply 4
Will it be delivered on time?
- Deadline Aug 2024, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 3 BHK
- 28 units, as declared to HRERA:
- 20 units averaging about 1,150 sq ft carpet (5 towers)
- 4 units of 4,527 sq ft carpet (1 tower)
- 4 units of 4,620 sq ft carpet (1 tower)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units.
- 7 plots, 1,759 sq yd
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 10.4 km by road (19 min by car)
- Cyber City 57 min · Airport 37 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
The builder: Experion Developers
- 16 projects registered in Gurugram, 3 lapsed
- 6 with an occupation certificate on record
- 74 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ZEPHYR AT THE WESTERLIES |
|---|---|
| Builder (promoter) | EXPERION DEVELOPERS PVT LTD |
| Location | SECTOR 108, GURUGRAM |
| RERA project ID | RERA-GRG-483-2019 |
| Registration certificate number | GGM/400/132/2020/16 DATED 22.06.2020 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 10/07/2024 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 0.3633 acres |
| Licence | Lisence No 57 of 2013 |
| Estimated cost of the project | ₹1,620.56 lakh (₹16.21 crore) |
| Total units (plots, apartments, shops) | 35 |
| Unit sizes (carpet area, as declared) | 20 units averaging about 1,150 sq ft carpet (5 towers); 4 units of 4,527 sq ft carpet (1 tower); 4 units of 4,620 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | 3 BHK (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 28-11-2019 |
| Building plans approved on | 28-11-2019 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-08-2020 |
|---|---|
| Likely completion date | 01-08-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against EXPERION DEVELOPERS PVT LTD (all its projects) | 74 (Complaint: 60; Compensation: 9; Execution of an earlier order: 5) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in